CONSTRUCTION LOOK FORWARD W/C 3RD AUGUST 2020

We are pleased to provide the following information regarding planned construction activity for the week commencing 3rd August 2020. Please note that the work we have planned may sometimes change. We will do our best to keep you updated with any material changes that may affect you.

This week, we will continue the concrete repair works to Block D columns adjacent to Co-operation Road, along with work to the concrete frame. We expect to generate some noise as we break out and excavate concrete externally for the provision of new drainage runs in the area adjacent to Block C, Block D and adjacent to Block F and Terrace 5 using excavators with pecker attachments, rollers and removal wagons. As always, we will monitor noise and vibration levels daily to ensure these continue to remain within permitted levels.

With regards to Block F, we will continue the erection of scaffolding to the front of the building while making minor adjustments to the existing scaffolding on other elevations. Other ongoing work in this area includes the removal of blockwork to both the front and rear elevations by our workforce on the scaffolding and removal of internal timber floors. There will be a continuation of the excavation of the ground internally along with the installation of drainage runs and works related to installing the new retaining walls externally, for which we will be using excavators with pecker attachments, dumpers, diggers and rollers both inside and outside. Internally, we will be installing new blockwork, fixing new brick ties and installing scaffolding which will generate some drilling noise as we safely fix this to the walls. On completion of the internal scaffold we will be beginning the removal of the roof timbers, starting with the South elevation.

Elsewhere on site, we will be continuing with the installation of scaffolding to Terrace 2 and Block E while commencing scaffold erection to Terrace 3. New brickwork will continue to Block E and Terrace 2 and commence for Terraces 3 and 4. During this week, we will commence installation of the pre-cast concrete floor and stairs to level 2 of Block E and we expect to take delivery of some large roof trusses along with some additional welfare units and other staff facilities.

A towable water bowser remains in use to dampen down work areas around the site on a regular basis. In addition to this, we have the provision of a water cannon which is being used for dust suppression which is situated in the area of Block F by the elevation closest to the Railway Path.

On social media please follow @ChocFactoryBris on Twitter, Facebook and Instagram as we will keep this updated with any relevant news and updates. For those without regular access to digital media, a community noticeboard is displayed on the hoarding at the entrance to site on Greenbank Road.

If you have any questions or concerns regarding work activities at any time please email chocfactoryresidents@sweetconstruct.co.uk