At this stage, we anticipate it taking 2 years to complete construction. This is dependent however on a number of factors such as weather and sales rates so is subject to change. Below is an overview of the activity we anticipate on site over the next three months.

November 2018

  • Installation of temporary site accommodation
  • Making good to temporary bases for site accommodation
  • Formation of site entrance
  • Installation of perimeter hoarding to entire site
  • Plant/skip deliveries and removals
  • Installation of Perimeter scaffolding to Block C
  • Asbestos resins removal to Block C – Low Risk. Brickwork repairs to Block C

December 2018

  • Temporary weather protection to windows in Block C
  • Asbestos resins removal to Block C – Low Risk
  • Securing site for the Christmas period
  • Brickwork repairs to Block C

January 2019

  • Commence installation of permanent Site accommodation
  • Commence roof repairs to Block C
  • Securing site for the Christmas period.
  • Continuation of work to Block C